AX Dynamic 365 implementation (DHHS) appears in 3 snapshots of the Victorian IT dashboard, from 2018-19 Q1 to 2018-19 Q3.
Its cost is $4.0m at 2018-19 Q3, against $3.4m at its baseline: +16%.
Its planned finish is 30 Jun 2020, 12 months later than the 30 Jun 2019 first planned.
Its latest rating is Green (2018-19 Q3), up from Red at 2018-19 Q1.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: AX Dynamic 365 implementation. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dhhsaxdynamic365implementation, as at 18 May 2026. Licence: CC BY 4.0.
How much does AX Dynamic 365 implementation cost? Its cost is $4.0m at 2018-19 Q3, against $3.4m at its baseline: +16%.
Is AX Dynamic 365 implementation late? Its planned finish is 30 Jun 2020, 12 months later than the 30 Jun 2019 first planned.
What is AX Dynamic 365 implementation's latest rating? Its latest rating is Green (2018-19 Q3), up from Red at 2018-19 Q1.