Disaster Recovery as a Service (DRaaS) (DH) appears in 12 snapshots of the Victorian IT dashboard, from 2021-22 Q1 to 2023-24 Q4.
Its cost is $17m at 2023-24 Q4, against $3.9m at its baseline: +350%.
Its planned finish is 30 Jun 2024, 12 months later than the 30 Jun 2023 first planned.
Its latest rating is Amber (2023-24 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Disaster Recovery as a Service (DRaaS). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dhdisasterrecoveryasaservicedraas, as at 18 May 2026. Licence: CC BY 4.0.
How much does Disaster Recovery as a Service (DRaaS) cost? Its cost is $17m at 2023-24 Q4, against $3.9m at its baseline: +350%.
Is Disaster Recovery as a Service (DRaaS) late? Its planned finish is 30 Jun 2024, 12 months later than the 30 Jun 2023 first planned.
What is Disaster Recovery as a Service (DRaaS)'s latest rating? Its latest rating is Amber (2023-24 Q4).