Consultative Councils Unit (CCU) Project - Phase 2 (DH) appears in 3 snapshots of the Victorian IT dashboard, from 2021-22 Q2 to 2021-22 Q4.
Its cost is $1.7m at 2021-22 Q4, against $1.4m at its baseline: +28%.
Its planned finish is 30 Jun 2022, 2 months later than the 29 Apr 2022 first planned.
Its latest rating is Green (2021-22 Q4).
The source marks it completed.