Network Evolution Project (DET) appears in 9 snapshots of the Victorian IT dashboard, from 2019-20 Q2 to 2021-22 Q2.
Its cost is $6.2m at 2021-22 Q2, against $7.4m at its baseline: -16%.
Its planned finish is 31 Dec 2021, 2 months later than the 11 Nov 2021 first planned.
Its latest rating is Green (2021-22 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Network Evolution Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/detnetworkevolutionproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does Network Evolution Project cost? Its cost is $6.2m at 2021-22 Q2, against $7.4m at its baseline: -16%.
Is Network Evolution Project late? Its planned finish is 31 Dec 2021, 2 months later than the 11 Nov 2021 first planned.
What is Network Evolution Project's latest rating? Its latest rating is Green (2021-22 Q2).