FSD-Oracle Cloud Program (DET) appears in 14 snapshots of the Victorian IT dashboard, from 2019-20 Q1 to 2022-23 Q2.
Its cost is $5.3m at 2022-23 Q2, against $2.9m at its baseline: +86%.
Its planned finish is 30 Apr 2024, 30 months later than the 1 Nov 2021 first planned.
Its latest rating is Amber (2022-23 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: FSD-Oracle Cloud Program. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/detfsdoraclecloudprogram, as at 18 May 2026. Licence: CC BY 4.0.
How much does FSD-Oracle Cloud Program cost? Its cost is $5.3m at 2022-23 Q2, against $2.9m at its baseline: +86%.
Is FSD-Oracle Cloud Program late? Its planned finish is 30 Apr 2024, 30 months later than the 1 Nov 2021 first planned.
What is FSD-Oracle Cloud Program's latest rating? Its latest rating is Amber (2022-23 Q2).