SupportED (formerly Student Support and Intervention) (DE) appears in 2 snapshots of the Victorian IT dashboard, from 2025-26 Q1 to 2025-26 Q2.
Its cost is $4.4m at 2025-26 Q2, against $3.7m at its baseline: +20%.
Its planned finish is 28 Nov 2025, 5 months later than the 30 Jun 2025 first planned.
Its latest rating is Green (2025-26 Q2), up from Amber at 2025-26 Q1.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: SupportED (formerly Student Support and Intervention). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/desupportedformerlystudentsupportandintervention, as at 18 May 2026. Licence: CC BY 4.0.
How much does SupportED (formerly Student Support and Intervention) cost? Its cost is $4.4m at 2025-26 Q2, against $3.7m at its baseline: +20%.
Is SupportED (formerly Student Support and Intervention) late? Its planned finish is 28 Nov 2025, 5 months later than the 30 Jun 2025 first planned.
What is SupportED (formerly Student Support and Intervention)'s latest rating? Its latest rating is Green (2025-26 Q2), up from Amber at 2025-26 Q1.