VGV Going Digital Project (DELWP) appears in 16 snapshots of the Victorian IT dashboard, from 2018-19 Q3 to 2022-23 Q2.
Its cost is $2.6m at 2022-23 Q2, against $0.5m at its baseline: +408%.
Its planned finish is 31 Mar 2023, 42 months later than the 30 Sep 2019 first planned.
Its latest rating is Green (2022-23 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: VGV Going Digital Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/delwpvgvgoingdigitalproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does VGV Going Digital Project cost? Its cost is $2.6m at 2022-23 Q2, against $0.5m at its baseline: +408%.
Is VGV Going Digital Project late? Its planned finish is 31 Mar 2023, 42 months later than the 30 Sep 2019 first planned.
What is VGV Going Digital Project's latest rating? Its latest rating is Green (2022-23 Q2).