Crown Land Information Improvement Project (CLIIP) (DELWP) appears in 15 snapshots of the Victorian IT dashboard, from 2016-17 Q4 to 2020-21 Q2.
Its cost is $3.9m at 2020-21 Q2, against $3.6m at its baseline: +8%.
Its planned finish is 30 Nov 2020, 16 months later than the 30 Jul 2019 first planned.
Its latest rating is Green (2020-21 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Crown Land Information Improvement Project (CLIIP). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/delwpcrownlandinformationimprovementprojectcliip, as at 18 May 2026. Licence: CC BY 4.0.
How much does Crown Land Information Improvement Project (CLIIP) cost? Its cost is $3.9m at 2020-21 Q2, against $3.6m at its baseline: +8%.
Is Crown Land Information Improvement Project (CLIIP) late? Its planned finish is 30 Nov 2020, 16 months later than the 30 Jul 2019 first planned.
What is Crown Land Information Improvement Project (CLIIP)'s latest rating? Its latest rating is Green (2020-21 Q2).