Infrastructure Portfolio Management (IPM) (DE) appears in 8 snapshots of the Victorian IT dashboard, from 2022-23 Q3 to 2024-25 Q2.
Its cost is $17m at 2024-25 Q2, against $6.7m at its baseline: +158%.
Its planned finish is 31 Oct 2024, 22 months later than the 31 Dec 2022 first planned.
Its latest rating is Green (2024-25 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Infrastructure Portfolio Management (IPM). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/deinfrastructureportfoliomanagementipm, as at 18 May 2026. Licence: CC BY 4.0.
How much does Infrastructure Portfolio Management (IPM) cost? Its cost is $17m at 2024-25 Q2, against $6.7m at its baseline: +158%.
Is Infrastructure Portfolio Management (IPM) late? Its planned finish is 31 Oct 2024, 22 months later than the 31 Dec 2022 first planned.
What is Infrastructure Portfolio Management (IPM)'s latest rating? Its latest rating is Green (2024-25 Q2).