FSD-Oracle Cloud Program (DE) appears in 4 snapshots of the Victorian IT dashboard, from 2022-23 Q3 to 2023-24 Q2.
Its cost is $5.3m at 2023-24 Q2, against $2.9m at its baseline: +86%.
Its planned finish is 11 Oct 2023, 23 months later than the 1 Nov 2021 first planned.
Its latest rating is Amber (2023-24 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: FSD-Oracle Cloud Program. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/defsdoraclecloudprogram, as at 18 May 2026. Licence: CC BY 4.0.
How much does FSD-Oracle Cloud Program cost? Its cost is $5.3m at 2023-24 Q2, against $2.9m at its baseline: +86%.
Is FSD-Oracle Cloud Program late? Its planned finish is 11 Oct 2023, 23 months later than the 1 Nov 2021 first planned.
What is FSD-Oracle Cloud Program's latest rating? Its latest rating is Amber (2023-24 Q2).