VicGrid Finance & Procurement - System Establishment (DEECA) appears in 3 snapshots of the Victorian IT dashboard, from 2024-25 Q3 to 2025-26 Q1.
Its planned finish is 31 Oct 2025, 4 months later than the 30 Jun 2025 first planned.
Its latest rating is Green (2025-26 Q1).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: VicGrid Finance & Procurement - System Establishment. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/deecavicgridfinanceprocurementsystemestablishment, as at 18 May 2026. Licence: CC BY 4.0.
Is VicGrid Finance & Procurement - System Establishment late? Its planned finish is 31 Oct 2025, 4 months later than the 30 Jun 2025 first planned.
What is VicGrid Finance & Procurement - System Establishment's latest rating? Its latest rating is Green (2025-26 Q1).