Resources Management System Victoria (RMSVIC) Project (DEECA) appears in 7 snapshots of the Victorian IT dashboard, from 2022-23 Q3 to 2024-25 Q1.
Its cost is $5.8m at 2024-25 Q1, against $5.9m at its baseline: -3%.
Its planned finish is 26 Aug 2024, 32 months later than the 31 Dec 2021 first planned.
Its latest rating is Red (2024-25 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Resources Management System Victoria (RMSVIC) Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/deecaresourcesmanagementsystemvictoriarmsvicproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does Resources Management System Victoria (RMSVIC) Project cost? Its cost is $5.8m at 2024-25 Q1, against $5.9m at its baseline: -3%.
Is Resources Management System Victoria (RMSVIC) Project late? Its planned finish is 26 Aug 2024, 32 months later than the 31 Dec 2021 first planned.
What is Resources Management System Victoria (RMSVIC) Project's latest rating? Its latest rating is Red (2024-25 Q1).