Inventory Management System Project (DEECA) appears in 4 snapshots of the Victorian IT dashboard, from 2024-25 Q1 to 2024-25 Q4.
Its cost is $2.1m at 2024-25 Q4, against $3.3m at its baseline: -35%.
Its planned finish is 30 Jun 2025, 17 months earlier than the 20 Nov 2026 first planned.
Its latest rating is Green (2024-25 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Inventory Management System Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/deecainventorymanagementsystemproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does Inventory Management System Project cost? Its cost is $2.1m at 2024-25 Q4, against $3.3m at its baseline: -35%.
Is Inventory Management System Project late? Its planned finish is 30 Jun 2025, 17 months earlier than the 20 Nov 2026 first planned.
What is Inventory Management System Project's latest rating? Its latest rating is Green (2024-25 Q4).