Expanding Victoria's Waste Data Systems (DEECA) appears in 10 snapshots of the Victorian IT dashboard, from 2022-23 Q3 to 2024-25 Q4.
Its cost is $7.1m at 2024-25 Q4, against $2.4m at its baseline: +191%.
Its planned finish is 30 Jun 2025, 12 months later than the 30 Jun 2024 first planned.
Its latest rating is Green (2024-25 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Expanding Victoria's Waste Data Systems. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/deecaexpandingvictoriaswastedatasystems, as at 18 May 2026. Licence: CC BY 4.0.
How much does Expanding Victoria's Waste Data Systems cost? Its cost is $7.1m at 2024-25 Q4, against $2.4m at its baseline: +191%.
Is Expanding Victoria's Waste Data Systems late? Its planned finish is 30 Jun 2025, 12 months later than the 30 Jun 2024 first planned.
What is Expanding Victoria's Waste Data Systems's latest rating? Its latest rating is Green (2024-25 Q4).