BriefUp Project (Ministerial Briefing System - MiBS Replacement) (DEECA) appears in 2 snapshots of the Victorian IT dashboard, from 2022-23 Q3 to 2022-23 Q4.
Its cost is $1.3m at 2022-23 Q4, against $1.2m at its baseline: +10%.
Its planned finish is 30 Jun 2023, 1 months later than the 23 May 2023 first planned.
Its latest rating is Green (2022-23 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: BriefUp Project (Ministerial Briefing System - MiBS Replacement). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/deecabriefupprojectministerialbriefingsystemmibsreplacement, as at 18 May 2026. Licence: CC BY 4.0.
How much does BriefUp Project (Ministerial Briefing System - MiBS Replacement) cost? Its cost is $1.3m at 2022-23 Q4, against $1.2m at its baseline: +10%.
Is BriefUp Project (Ministerial Briefing System - MiBS Replacement) late? Its planned finish is 30 Jun 2023, 1 months later than the 23 May 2023 first planned.
What is BriefUp Project (Ministerial Briefing System - MiBS Replacement)'s latest rating? Its latest rating is Green (2022-23 Q4).