Arc Learning (FUSE Replacement) (DE) appears in 5 snapshots of the Victorian IT dashboard, from 2022-23 Q3 to 2023-24 Q3.
Its cost is $3.4m at 2023-24 Q3, against $1.7m at its baseline: +106%.
Its planned finish is 29 Mar 2024, 9 months later than the 30 Jun 2023 first planned.
Its latest rating is Green (2023-24 Q3), up from Amber at 2022-23 Q3.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Arc Learning (FUSE Replacement). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/dearclearningfusereplacement, as at 18 May 2026. Licence: CC BY 4.0.
How much does Arc Learning (FUSE Replacement) cost? Its cost is $3.4m at 2023-24 Q3, against $1.7m at its baseline: +106%.
Is Arc Learning (FUSE Replacement) late? Its planned finish is 29 Mar 2024, 9 months later than the 30 Jun 2023 first planned.
What is Arc Learning (FUSE Replacement)'s latest rating? Its latest rating is Green (2023-24 Q3), up from Amber at 2022-23 Q3.