CRM Platform Upgrade (DET) appears in 2 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2015-16 Q4.
Its cost is $0.5m at 2015-16 Q4, against $1.0m at its baseline: -45%.
Its planned finish is 26 May 2016, 5 months earlier than the 13 Oct 2016 first planned.
Its latest rating is Green (2015-16 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: CRM Platform Upgrade. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/d6c63789-4cd5-44d9-abd4-52e25acb4082, as at 18 May 2026. Licence: CC BY 4.0.
How much does CRM Platform Upgrade cost? Its cost is $0.5m at 2015-16 Q4, against $1.0m at its baseline: -45%.
Is CRM Platform Upgrade late? Its planned finish is 26 May 2016, 5 months earlier than the 13 Oct 2016 first planned.