HSEQ (1006412) (CW Water) appears in 6 snapshots of the Victorian IT dashboard, from 2017-18 Q4 to 2019-20 Q1.
Its cost is $1.5m at 2019-20 Q1, against $1.2m at its baseline: +22%.
Its planned finish is 14 Jul 2019, 5 months later than the 1 Feb 2019 first planned.
Its latest rating is Green (2019-20 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: HSEQ (1006412). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/cwwaterhseq1006412, as at 18 May 2026. Licence: CC BY 4.0.
How much does HSEQ (1006412) cost? Its cost is $1.5m at 2019-20 Q1, against $1.2m at its baseline: +22%.
Is HSEQ (1006412) late? Its planned finish is 14 Jul 2019, 5 months later than the 1 Feb 2019 first planned.
What is HSEQ (1006412)'s latest rating? Its latest rating is Green (2019-20 Q1).