EDRMS Implementation (CW Water) appears in 5 snapshots of the Victorian IT dashboard, from 2019-20 Q1 to 2020-21 Q1.
Its planned finish is 24 Aug 2020, 2 months later than the 30 Jun 2020 first planned.
Its latest rating is Green (2020-21 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: EDRMS Implementation. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/cwwateredrmsimplementation, as at 18 May 2026. Licence: CC BY 4.0.
Is EDRMS Implementation late? Its planned finish is 24 Aug 2020, 2 months later than the 30 Jun 2020 first planned.
What is EDRMS Implementation's latest rating? Its latest rating is Green (2020-21 Q1).