Data and Analytics (1006380) (CW Water) appears in 3 snapshots of the Victorian IT dashboard, from 2017-18 Q4 to 2018-19 Q2.
Its planned finish is 30 Nov 2018, 12 months earlier than the 30 Nov 2019 first planned.
Its latest rating is Green (2018-19 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Data and Analytics (1006380). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/cwwaterdataandanalytics1006380, as at 18 May 2026. Licence: CC BY 4.0.
Is Data and Analytics (1006380) late? Its planned finish is 30 Nov 2018, 12 months earlier than the 30 Nov 2019 first planned.
What is Data and Analytics (1006380)'s latest rating? Its latest rating is Green (2018-19 Q2).