Digital Metering Program (CHR Water) appears in 14 snapshots of the Victorian IT dashboard, from 2022-23 Q1 to 2025-26 Q2.
Its cost is $21m at 2025-26 Q2, against $20m at its baseline: +6%.
Its planned finish is 30 Dec 2026, 3 months later than the 30 Sep 2026 first planned.
Its latest rating is Green (2025-26 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Digital Metering Program. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/chrwaterdigitalmeteringprogram, as at 18 May 2026. Licence: CC BY 4.0.
How much does Digital Metering Program cost? Its cost is $21m at 2025-26 Q2, against $20m at its baseline: +6%.
Is Digital Metering Program late? Its planned finish is 30 Dec 2026, 3 months later than the 30 Sep 2026 first planned.
What is Digital Metering Program's latest rating? Its latest rating is Green (2025-26 Q2).