Structural Migration and PC Refresh (CenITex) appears in 4 snapshots of the Victorian IT dashboard, from 2019-20 Q2 to 2020-21 Q1.
Its planned finish is 30 Sep 2020, 5 months later than the 1 May 2020 first planned.
Its latest rating is Green (2020-21 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Structural Migration and PC Refresh. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/cenitexstructuralmigrationandpcrefresh, as at 18 May 2026. Licence: CC BY 4.0.
Is Structural Migration and PC Refresh late? Its planned finish is 30 Sep 2020, 5 months later than the 1 May 2020 first planned.
What is Structural Migration and PC Refresh's latest rating? Its latest rating is Green (2020-21 Q1).