Software Defined Datacentre (SDDC) Migration (CenITex) appears in 4 snapshots of the Victorian IT dashboard, from 2024-25 Q3 to 2025-26 Q2.
Its cost is $1.4m at 2025-26 Q2, against $1.4m at its baseline: -0%.
Its planned finish is 28 Feb 2026, 3 months later than the 30 Nov 2025 first planned.
Its latest rating is Green (2025-26 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Software Defined Datacentre (SDDC) Migration. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/cenitexsoftwaredefineddatacentresddcmigration, as at 18 May 2026. Licence: CC BY 4.0.
How much does Software Defined Datacentre (SDDC) Migration cost? Its cost is $1.4m at 2025-26 Q2, against $1.4m at its baseline: -0%.
Is Software Defined Datacentre (SDDC) Migration late? Its planned finish is 28 Feb 2026, 3 months later than the 30 Nov 2025 first planned.
What is Software Defined Datacentre (SDDC) Migration's latest rating? Its latest rating is Green (2025-26 Q2).