IPS Uplift (CenITex) appears in 12 snapshots of the Victorian IT dashboard, from 2021-22 Q1 to 2023-24 Q4.
Its cost is $2.2m at 2023-24 Q4, against $1.5m at its baseline: +49%.
Its planned finish is 30 Apr 2024, 28 months later than the 31 Dec 2021 first planned.
Its latest rating is Green (2023-24 Q4), up from Amber at 2021-22 Q1.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: IPS Uplift. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/cenitexipsuplift, as at 18 May 2026. Licence: CC BY 4.0.
How much does IPS Uplift cost? Its cost is $2.2m at 2023-24 Q4, against $1.5m at its baseline: +49%.
Is IPS Uplift late? Its planned finish is 30 Apr 2024, 28 months later than the 31 Dec 2021 first planned.
What is IPS Uplift's latest rating? Its latest rating is Green (2023-24 Q4), up from Amber at 2021-22 Q1.