Hybrid Cloud Program: Mediation Layer - Stage 1 (CenITex) appears in 8 snapshots of the Victorian IT dashboard, from 2022-23 Q3 to 2024-25 Q2.
Its cost is $5.9m at 2024-25 Q2, against $3.6m at its baseline: +62%.
Its planned finish is 31 Oct 2024, 28 months later than the 30 Jun 2022 first planned.
Its latest rating is Green (2024-25 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Hybrid Cloud Program: Mediation Layer - Stage 1. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/cenitexhybridcloudprogrammediationlayerstage1, as at 18 May 2026. Licence: CC BY 4.0.
How much does Hybrid Cloud Program: Mediation Layer - Stage 1 cost? Its cost is $5.9m at 2024-25 Q2, against $3.6m at its baseline: +62%.
Is Hybrid Cloud Program: Mediation Layer - Stage 1 late? Its planned finish is 31 Oct 2024, 28 months later than the 30 Jun 2022 first planned.