DC Exit Network Establishment – Phase 2 (CenITex) appears in 5 snapshots of the Victorian IT dashboard, from 2024-25 Q2 to 2025-26 Q2.
Its cost is $3.0m at 2025-26 Q2, against $2.0m at its baseline: +50%.
Its planned finish is 28 Feb 2026, 4 months later than the 30 Oct 2025 first planned.
Its latest rating is Green (2025-26 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: DC Exit Network Establishment – Phase 2. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/cenitexdcexitnetworkestablishmentphase2, as at 18 May 2026. Licence: CC BY 4.0.
How much does DC Exit Network Establishment – Phase 2 cost? Its cost is $3.0m at 2025-26 Q2, against $2.0m at its baseline: +50%.
Is DC Exit Network Establishment – Phase 2 late? Its planned finish is 28 Feb 2026, 4 months later than the 30 Oct 2025 first planned.
What is DC Exit Network Establishment – Phase 2's latest rating? Its latest rating is Green (2025-26 Q2).