Data Centre Network Design and Infrastructure Establishment (CenITex) appears in 7 snapshots of the Victorian IT dashboard, from 2017-18 Q2 to 2018-19 Q4.
Its cost is $2.8m at 2018-19 Q4, against $2.8m at its baseline: +1%.
Its planned finish is 30 Jun 2019, 12 months later than the 30 Jun 2018 first planned.
Its latest rating is Green (2018-19 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Data Centre Network Design and Infrastructure Establishment. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/cenitexdatacentrenetworkdesignandinfrastructureestablishment, as at 18 May 2026. Licence: CC BY 4.0.
How much does Data Centre Network Design and Infrastructure Establishment cost? Its cost is $2.8m at 2018-19 Q4, against $2.8m at its baseline: +1%.
Is Data Centre Network Design and Infrastructure Establishment late? Its planned finish is 30 Jun 2019, 12 months later than the 30 Jun 2018 first planned.
What is Data Centre Network Design and Infrastructure Establishment's latest rating? Its latest rating is Green (2018-19 Q4).