Integration Platform Refresh for WorkSafe (WSV) appears in 6 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2016-17 Q4.
Its cost is $0.6m at 2016-17 Q4, against $0.3m at its baseline: +83%.
Its planned finish is 31 Jul 2016, 1 months later than the 30 Jun 2016 first planned.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Integration Platform Refresh for WorkSafe. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/c985dc72-c877-475a-9189-aa80c5d7b729, as at 18 May 2026. Licence: CC BY 4.0.
How much does Integration Platform Refresh for WorkSafe cost? Its cost is $0.6m at 2016-17 Q4, against $0.3m at its baseline: +83%.
Is Integration Platform Refresh for WorkSafe late? Its planned finish is 31 Jul 2016, 1 months later than the 30 Jun 2016 first planned.