C1443 - Land Development and New Connections Transformation (BR Water) appears in 7 snapshots of the Victorian IT dashboard, from 2023-24 Q3 to 2025-26 Q1.
Its cost is $1.3m at 2025-26 Q1, against $1.4m at its baseline: -5%.
Its planned finish is 31 Jul 2025, 10 months later than the 30 Sep 2024 first planned.
Its latest rating is Green (2025-26 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: C1443 - Land Development and New Connections Transformation. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/brwaterc1443landdevelopmentandnewconnectionstransformation, as at 18 May 2026. Licence: CC BY 4.0.
How much does C1443 - Land Development and New Connections Transformation cost? Its cost is $1.3m at 2025-26 Q1, against $1.4m at its baseline: -5%.
Is C1443 - Land Development and New Connections Transformation late? Its planned finish is 31 Jul 2025, 10 months later than the 30 Sep 2024 first planned.
What is C1443 - Land Development and New Connections Transformation's latest rating? Its latest rating is Green (2025-26 Q1).