C1430 - Network Segmentation (BR Water) appears in 8 snapshots of the Victorian IT dashboard, from 2023-24 Q3 to 2025-26 Q2.
Its cost is $3.0m at 2025-26 Q2, against $1.5m at its baseline: +102%.
Its planned finish is 31 Aug 2026, 22 months later than the 7 Nov 2024 first planned.
Its latest rating is Amber (2025-26 Q2), up from Red at 2023-24 Q3.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: C1430 - Network Segmentation. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/brwaterc1430networksegmentation, as at 18 May 2026. Licence: CC BY 4.0.
How much does C1430 - Network Segmentation cost? Its cost is $3.0m at 2025-26 Q2, against $1.5m at its baseline: +102%.
Is C1430 - Network Segmentation late? Its planned finish is 31 Aug 2026, 22 months later than the 7 Nov 2024 first planned.
What is C1430 - Network Segmentation's latest rating? Its latest rating is Amber (2025-26 Q2), up from Red at 2023-24 Q3.