C1400 - M365 Phase 3 (BR Water) appears in 7 snapshots of the Victorian IT dashboard, from 2022-23 Q3 to 2024-25 Q1.
Its cost is $2.2m at 2024-25 Q1, against $1.3m at its baseline: +73%.
Its planned finish is 30 Aug 2024, 14 months later than the 30 Jun 2023 first planned.
Its latest rating is Green (2024-25 Q1), up from Amber at 2022-23 Q3.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: C1400 - M365 Phase 3. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/brwaterc1400m365phase3, as at 18 May 2026. Licence: CC BY 4.0.
How much does C1400 - M365 Phase 3 cost? Its cost is $2.2m at 2024-25 Q1, against $1.3m at its baseline: +73%.
Is C1400 - M365 Phase 3 late? Its planned finish is 30 Aug 2024, 14 months later than the 30 Jun 2023 first planned.
What is C1400 - M365 Phase 3's latest rating? Its latest rating is Green (2024-25 Q1), up from Amber at 2022-23 Q3.