C1220 Sherwin 4CX Project (BR Water) appears in 12 snapshots of the Victorian IT dashboard, from 2019-20 Q1 to 2021-22 Q4.
Its cost is $1.9m at 2021-22 Q4, against $1.8m at its baseline: +3%.
Its planned finish is 31 May 2022, 18 months later than the 28 Nov 2020 first planned.
Its latest rating is Green (2021-22 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: C1220 Sherwin 4CX Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/brwaterc1220sherwin4cxproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does C1220 Sherwin 4CX Project cost? Its cost is $1.9m at 2021-22 Q4, against $1.8m at its baseline: +3%.
Is C1220 Sherwin 4CX Project late? Its planned finish is 31 May 2022, 18 months later than the 28 Nov 2020 first planned.
What is C1220 Sherwin 4CX Project's latest rating? Its latest rating is Green (2021-22 Q4).