C1044 Asset Register Replacement Project (BR Water) appears in 5 snapshots of the Victorian IT dashboard, from 2019-20 Q1 to 2020-21 Q1.
Its cost is $2.3m at 2020-21 Q1, against $1.7m at its baseline: +39%.
Its planned finish is 31 Aug 2020, 7 months later than the 14 Feb 2020 first planned.
Its latest rating is Green (2020-21 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: C1044 Asset Register Replacement Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/brwaterc1044assetregisterreplacementproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does C1044 Asset Register Replacement Project cost? Its cost is $2.3m at 2020-21 Q1, against $1.7m at its baseline: +39%.
Is C1044 Asset Register Replacement Project late? Its planned finish is 31 Aug 2020, 7 months later than the 14 Feb 2020 first planned.
What is C1044 Asset Register Replacement Project's latest rating? Its latest rating is Green (2020-21 Q1).