Project Synergy (BKI TAFE) appears in 10 snapshots of the Victorian IT dashboard, from 2022-23 Q3 to 2024-25 Q4.
Its cost is $2.2m at 2024-25 Q4, against $2.0m at its baseline: +9%.
Its planned finish is 30 Sep 2024, 8 months later than the 6 Feb 2024 first planned.
Its latest rating is Red (2024-25 Q4), down from Green at 2022-23 Q3.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Project Synergy. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/bkitafeprojectsynergy, as at 18 May 2026. Licence: CC BY 4.0.
How much does Project Synergy cost? Its cost is $2.2m at 2024-25 Q4, against $2.0m at its baseline: +9%.
Is Project Synergy late? Its planned finish is 30 Sep 2024, 8 months later than the 6 Feb 2024 first planned.
What is Project Synergy's latest rating? Its latest rating is Red (2024-25 Q4), down from Green at 2022-23 Q3.