Emergency Alert Phase 3 - Delivery (DJR) appears in 4 snapshots of the Victorian IT dashboard, from 2016-17 Q1 to 2016-17 Q4.
Its planned finish is 30 Jun 2017, 11 months later than the 25 Jul 2016 first planned.
Its latest rating is Green (2016-17 Q4), up from Amber at 2016-17 Q1.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Emergency Alert Phase 3 - Delivery. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/bffbd9be-a506-4455-af71-75d06fa8b864, as at 18 May 2026. Licence: CC BY 4.0.
Is Emergency Alert Phase 3 - Delivery late? Its planned finish is 30 Jun 2017, 11 months later than the 25 Jul 2016 first planned.
What is Emergency Alert Phase 3 - Delivery's latest rating? Its latest rating is Green (2016-17 Q4), up from Amber at 2016-17 Q1.