Train SCADA (Electrol) Replacement (PTV) appears in 7 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2017-18 Q1.
Its cost is $30m at 2017-18 Q1, against $31m at its baseline: -1%.
Its planned finish is 29 Sep 2017, 14 months later than the 30 Jul 2016 first planned.
Its latest rating is Green (2017-18 Q1), up from Amber at 2015-16 Q3.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Train SCADA (Electrol) Replacement. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/bf7990aa-e1d3-4af4-862c-4960c8a9949b, as at 18 May 2026. Licence: CC BY 4.0.
How much does Train SCADA (Electrol) Replacement cost? Its cost is $30m at 2017-18 Q1, against $31m at its baseline: -1%.
Is Train SCADA (Electrol) Replacement late? Its planned finish is 29 Sep 2017, 14 months later than the 30 Jul 2016 first planned.
What is Train SCADA (Electrol) Replacement's latest rating? Its latest rating is Green (2017-18 Q1), up from Amber at 2015-16 Q3.