Upgrade project - Electronic Document and Records Management System (eDRMS) Upgrade (DJR) appears in 7 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2017-18 Q1.
Its cost is $3.5m at 2017-18 Q1, against $3.5m at its baseline: +1%.
Its planned finish is 31 Jul 2017, 12 months later than the 31 Jul 2016 first planned.
Its latest rating is Green (2017-18 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Upgrade project - Electronic Document and Records Management System (eDRMS) Upgrade. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/b65282bf-398b-481c-a821-e4aaaac6b0bc, as at 18 May 2026. Licence: CC BY 4.0.
How much does Upgrade project - Electronic Document and Records Management System (eDRMS) Upgrade cost? Its cost is $3.5m at 2017-18 Q1, against $3.5m at its baseline: +1%.
Is Upgrade project - Electronic Document and Records Management System (eDRMS) Upgrade late? Its planned finish is 31 Jul 2017, 12 months later than the 31 Jul 2016 first planned.
What is Upgrade project - Electronic Document and Records Management System (eDRMS) Upgrade's latest rating? Its latest rating is Green (2017-18 Q1).