VACIS Modernisation Device Pilot (AVS) appears in 7 snapshots of the Victorian IT dashboard, from 2023-24 Q2 to 2024-25 Q4.
Its cost is $2.4m at 2024-25 Q4, against $3.2m at its baseline: -26%.
Its planned finish is 30 Jun 2025, 6 months later than the 31 Dec 2024 first planned.
Its latest rating is Green (2024-25 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: VACIS Modernisation Device Pilot. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/avsvacismodernisationdevicepilot, as at 18 May 2026. Licence: CC BY 4.0.
How much does VACIS Modernisation Device Pilot cost? Its cost is $2.4m at 2024-25 Q4, against $3.2m at its baseline: -26%.
Is VACIS Modernisation Device Pilot late? Its planned finish is 30 Jun 2025, 6 months later than the 31 Dec 2024 first planned.
What is VACIS Modernisation Device Pilot's latest rating? Its latest rating is Green (2024-25 Q4).