Clinical Technology Refresh 2019/20 – Upgrade End-Of-Life Windows/ SQL Server 2008 systems to latest Windows/ SQL Server version (ALFRED) appears in 4 snapshots of the Victorian IT dashboard, from 2019-20 Q4 to 2020-21 Q3.
Its cost is $1.4m at 2020-21 Q3, against $1.4m at its baseline: no change.
Its planned finish is 31 Mar 2021, 5 months later than the 31 Oct 2020 first planned.
Its latest rating is Green (2020-21 Q3).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Clinical Technology Refresh 2019/20 – Upgrade End-Of-Life Windows/ SQL Server 2008 systems to latest Windows/ SQL Server version. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/alfredclinicaltechnologyrefresh201920upgradeendoflifewindowssqlserver2008systemstolatestwindowssqlserverversion, as at 18 May 2026. Licence: CC BY 4.0.
How much does Clinical Technology Refresh 2019/20 – Upgrade End-Of-Life Windows/ SQL Server 2008 systems to latest Windows/ SQL Server version cost? Its cost is $1.4m at 2020-21 Q3, against $1.4m at its baseline: no change.
Is Clinical Technology Refresh 2019/20 – Upgrade End-Of-Life Windows/ SQL Server 2008 systems to latest Windows/ SQL Server version late? Its planned finish is 31 Mar 2021, 5 months later than the 31 Oct 2020 first planned.
What is Clinical Technology Refresh 2019/20 – Upgrade End-Of-Life Windows/ SQL Server 2008 systems to latest Windows/ SQL Server version's latest rating? Its latest rating is Green (2020-21 Q3).