R&L Digital Services Transformation (Stage 1) (VicRoads) appears in 2 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2015-16 Q4.
Its cost is $20m at 2015-16 Q4, against $20m at its baseline: -0%.
Its planned finish is 30 Jun 2016, 6 months earlier than the 30 Dec 2016 first planned.
Its latest rating is Green (2015-16 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: R&L Digital Services Transformation (Stage 1). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/acaa86ae-d19b-497b-ae60-5376a1a8c6c5, as at 18 May 2026. Licence: CC BY 4.0.
How much does R&L Digital Services Transformation (Stage 1) cost? Its cost is $20m at 2015-16 Q4, against $20m at its baseline: -0%.
Is R&L Digital Services Transformation (Stage 1) late? Its planned finish is 30 Jun 2016, 6 months earlier than the 30 Dec 2016 first planned.
What is R&L Digital Services Transformation (Stage 1)'s latest rating? Its latest rating is Green (2015-16 Q4).