Network Transformation - Analogue Gateway (VicTrack) appears in 6 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2016-17 Q4.
Its cost is $1.2m at 2016-17 Q4, against $1.8m at its baseline: -33%.
Its planned finish is 13 Apr 2017, 4 months later than the 30 Nov 2016 first planned.
Its latest rating is Green (2016-17 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Network Transformation - Analogue Gateway. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/a7965c46-bff4-4ebc-b7aa-c00516d1330c, as at 18 May 2026. Licence: CC BY 4.0.
How much does Network Transformation - Analogue Gateway cost? Its cost is $1.2m at 2016-17 Q4, against $1.8m at its baseline: -33%.
Is Network Transformation - Analogue Gateway late? Its planned finish is 13 Apr 2017, 4 months later than the 30 Nov 2016 first planned.
What is Network Transformation - Analogue Gateway's latest rating? Its latest rating is Green (2016-17 Q4).