Shared Storage & Backup Refresh (CTX) appears in 6 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2016-17 Q4.
Its cost is $7.3m at 2016-17 Q4, against $7.0m at its baseline: +4%.
Its planned finish is 30 Dec 2016, 6 months later than the 30 Jun 2016 first planned.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Shared Storage & Backup Refresh. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/9f6b93e7-4787-44d2-aa55-43b016ab8d05, as at 18 May 2026. Licence: CC BY 4.0.
How much does Shared Storage & Backup Refresh cost? Its cost is $7.3m at 2016-17 Q4, against $7.0m at its baseline: +4%.
Is Shared Storage & Backup Refresh late? Its planned finish is 30 Dec 2016, 6 months later than the 30 Jun 2016 first planned.