EPSILON (VRQA) appears in 7 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2017-18 Q1.
Its cost is $4.1m at 2017-18 Q1, against $2.3m at its baseline: +79%.
Its planned finish is 25 Jun 2018, 22 months later than the 22 Aug 2016 first planned.
Its latest rating is Green (2017-18 Q1).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: EPSILON. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/9e7a0013-0e70-496e-b229-2fa0b18a7599, as at 18 May 2026. Licence: CC BY 4.0.
How much does EPSILON cost? Its cost is $4.1m at 2017-18 Q1, against $2.3m at its baseline: +79%.
Is EPSILON late? Its planned finish is 25 Jun 2018, 22 months later than the 22 Aug 2016 first planned.
What is EPSILON's latest rating? Its latest rating is Green (2017-18 Q1).