Alchemy Project (CHR Water) appears in 2 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2015-16 Q4.
Its cost is $3.5m at 2015-16 Q4, against $2.7m at its baseline: +29%.
Its planned finish is 30 Jun 2016, 9 months later than the 30 Sep 2015 first planned.
Its latest rating is Green (2015-16 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Alchemy Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/8c4dd9a5-db2c-40cf-90a8-b9f15ce0b37c, as at 18 May 2026. Licence: CC BY 4.0.
How much does Alchemy Project cost? Its cost is $3.5m at 2015-16 Q4, against $2.7m at its baseline: +29%.
Is Alchemy Project late? Its planned finish is 30 Jun 2016, 9 months later than the 30 Sep 2015 first planned.
What is Alchemy Project's latest rating? Its latest rating is Green (2015-16 Q4).