Asset Management System Replacement (DET) appears in 6 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2016-17 Q4.
Its cost is $5.2m at 2016-17 Q4, against $5.3m at its baseline: -1%.
Its planned finish is 21 Jul 2017, 12 months later than the 25 Jul 2016 first planned.
Its latest rating is Green (2016-17 Q4), up from Amber at 2015-16 Q3.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Asset Management System Replacement. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/891f2445-1ae7-411e-b7dd-cbb33725a606, as at 18 May 2026. Licence: CC BY 4.0.
How much does Asset Management System Replacement cost? Its cost is $5.2m at 2016-17 Q4, against $5.3m at its baseline: -1%.
Is Asset Management System Replacement late? Its planned finish is 21 Jul 2017, 12 months later than the 25 Jul 2016 first planned.
What is Asset Management System Replacement's latest rating? Its latest rating is Green (2016-17 Q4), up from Amber at 2015-16 Q3.