DEDJTR ICT Transition Program (DEDJTR) appears in 6 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2016-17 Q4.
Its cost is $9.5m at 2016-17 Q4, against $9.5m at its baseline: no change.
Its planned finish is 23 Dec 2016, 3 months later than the 30 Sep 2016 first planned.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: DEDJTR ICT Transition Program. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/856fc387-1720-40e8-bef1-e8bf59874dca, as at 18 May 2026. Licence: CC BY 4.0.
How much does DEDJTR ICT Transition Program cost? Its cost is $9.5m at 2016-17 Q4, against $9.5m at its baseline: no change.
Is DEDJTR ICT Transition Program late? Its planned finish is 23 Dec 2016, 3 months later than the 30 Sep 2016 first planned.