ESTA Triple Zero Service Communications Enhancements (ESTA) appears in 2 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2015-16 Q4.
Its cost is $12m at 2015-16 Q4, against $13m at its baseline: -7%.
Its planned finish is 30 Jun 2016, 4 months later than the 29 Feb 2016 first planned.
Its latest rating is Green (2015-16 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: ESTA Triple Zero Service Communications Enhancements. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/7efd35f9-0897-476f-a4ab-f0b0d92f4c00, as at 18 May 2026. Licence: CC BY 4.0.
How much does ESTA Triple Zero Service Communications Enhancements cost? Its cost is $12m at 2015-16 Q4, against $13m at its baseline: -7%.
Is ESTA Triple Zero Service Communications Enhancements late? Its planned finish is 30 Jun 2016, 4 months later than the 29 Feb 2016 first planned.
What is ESTA Triple Zero Service Communications Enhancements's latest rating? Its latest rating is Green (2015-16 Q4).