Relocation Project (Peter Mac) appears in 6 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2016-17 Q4.
Its cost is $4.0m at 2016-17 Q4, against $0.9m at its baseline: +325%.
Its planned finish is 30 Sep 2016, 2 months later than the 29 Jul 2016 first planned.
Its latest rating is Green (2016-17 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Relocation Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/64bf4a07-d43b-4e7c-a725-d5db05182a4f, as at 18 May 2026. Licence: CC BY 4.0.
How much does Relocation Project cost? Its cost is $4.0m at 2016-17 Q4, against $0.9m at its baseline: +325%.
Is Relocation Project late? Its planned finish is 30 Sep 2016, 2 months later than the 29 Jul 2016 first planned.
What is Relocation Project's latest rating? Its latest rating is Green (2016-17 Q4).