Enterprise Content Management System (DELWP) appears in 6 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2016-17 Q4.
Its cost is $6.3m at 2016-17 Q4, against $6.0m at its baseline: +5%.
Its planned finish is 28 Feb 2017, 10 months later than the 30 Apr 2016 first planned.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Enterprise Content Management System. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/5ff8e95c-6029-43f1-a725-b025b25cf43d, as at 18 May 2026. Licence: CC BY 4.0.
How much does Enterprise Content Management System cost? Its cost is $6.3m at 2016-17 Q4, against $6.0m at its baseline: +5%.
Is Enterprise Content Management System late? Its planned finish is 28 Feb 2017, 10 months later than the 30 Apr 2016 first planned.