Arrow Program (CWW) appears in 7 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2017-18 Q1.
Its cost is $114m at 2017-18 Q1, against $104m at its baseline: +10%.
Its planned finish is 30 Jun 2019, 36 months earlier than the 30 Jun 2022 first planned.
Its latest rating is Green (2017-18 Q1), up from Amber at 2015-16 Q3.